action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/wp-includes/functions.php on line 6114The new main shop was designed to house 25 vehicles including 14 plow trucks, 3 large vehicle repair bays, 2 small vehicle repair bays, a sign shop, a parts storage room, a fully automated truck wash, crew lockers, a lunchroom, and offices for the entire department.
The site includes a 12K gallon fueling station and canopy, outdoor stock storage, stormwater, and parking. Master planning for salt sheds and cold storage was incorporated into the design to be completed as needed in the future. Barrientos Design was hired to design full architectural plans and oversee construction administration.
Size: 44,700 SF
Cost: $7.6M
Completion: 2018